Trades on site: who does what and when
In partial self-build, you are the conductor: you coordinate the trades with each other and with your own work. An electrician arriving before the dry liner has finished, a tiler waiting three weeks for a screed, a plumber drilling through an already-insulated wall… Every sequencing mistake costs time and money. Here is the precise order in which each trade should arrive on site, and how to coordinate them in your Gantt chart.
The order of trades: the golden rule
The sequence of trades follows an immutable logic: work from structural to finish, from outside to inside, from floor to ceiling.
Phase 1: Groundworks and foundations
| Order | Trade | What they do | Duration |
|---|---|---|---|
| 1 | Land surveyor | Set out the building on the plot | 1 day |
| 2 | Groundworker | Excavation, trenches, utilities | 2–5 days |
| 3 | Bricklayer / Blocklayer | Strip foundations, substructure, slab | 2–4 weeks |
Tip — The groundworker and the bricklayer must coordinate closely: the groundworker digs the trenches, the bricklayer checks the bottom of the excavation and pours the concrete promptly. If the bottom of the trench is left open too long (rain, collapse), it will need to be dug out again.
Phase 2: Structural shell
| Order | Trade | What they do | Duration |
|---|---|---|---|
| 4 | Bricklayer / Blocklayer | Load-bearing walls, ring beams, lintels | 4–8 weeks |
| 5 | Carpenter / Roofer | Roof structure (cut roof or trusses) | 1–2 weeks |
| 6 | Roofer | Tiles, slates, leadwork → watertight | 1–2 weeks |
| 7 | Joiner (1st fix ext.) | Windows, front door, external doors → weathertight | 1 week |
Warning — The carpenter cannot start until the bricklayer has finished the ring beam at wall-plate level. And the roofer cannot tile without a breathable roofing membrane. Each trade depends on the previous one — a 3-day delay from the bricklayer pushes the carpenter, who pushes the roofer, who pushes the entire second-fix programme.
Phase 3: Second fix — the critical sequence
This is the phase where sequencing is most delicate. Here is the exact order:
| Order | Trade | What they do | Depends on |
|---|---|---|---|
| 8 | Electrician (1st fix) | Conduit, back boxes, temporary consumer unit | Weathertight |
| 9 | Plumber (1st fix) | Supply and waste pipes in walls | Weathertight |
| 10 | Heating engineer | Heating circuit (underfloor heating: before screed) | Weathertight |
| 11 | Insulation contractor | Insulation to walls, roof, floor | After elec + plumbing 1st fix |
| 12 | Dry liner / Plasterer | Stud walls, wall linings, tape and joint | After insulation |
| 13 | Screeder | Traditional or liquid screed | After plasterboard |
| 14 | (Screed drying: 3 weeks) | — | — |
| 15 | Waterproofer / Tanker | Wet room tanking (bathroom, kitchen) | After dry screed |
| 16 | Tiler | Floor and wall tiles | After tanking |
| 17 | Decorator | Walls and ceilings | After dry plasterboard + tape |
| 18 | Electrician (2nd fix) | Sockets, switches, light fittings | After decorating |
| 19 | Plumber (2nd fix) | Taps, WC, sanitaryware | After tiling |
| 20 | Joiner / Carpenter (2nd fix) | Doors, skirtings, fitted wardrobes | After decorating |

Best practice — The electrician and plumber doing 1st fix work in parallel (steps 8 and 9). This is one of the rare moments when two trades can work simultaneously without getting in each other’s way — provided they coordinate on penetrations through shared stud walls.
Tasks you can do yourself
In partial self-build, here is what most self-builders typically take on:
| Task | DIY difficulty | Prerequisites |
|---|---|---|
| Insulating walls and roof space | Easy | After 1st fix |
| Plasterboard + tape and joint | Medium | Training or video tutorial |
| Floor tiling | Medium | Dry screed + tanking |
| Decorating | Easy | After dry tape and joint |
| Hanging internal doors | Easy | After decorating |
| Fitting kitchen | Medium | After tiling + 2nd fix |
| External landscaping | Variable | Last of all |
Tip — Slot your own work between the tradespeople’s visits. For example: the plumber finishes 1st fix on Friday → you insulate the walls over the weekend → the dry liner starts on Monday. This is the key to saving time without creating dead time.
Coordination pitfalls
1. The trade who doesn’t show up
This is the number one problem. A trade who slips by a week blocks the entire chain.
Solutions:
- Confirm every visit 1 week and 48 hours in advance.
- Have a backup contact for every critical trade.
- Build in 1 week of float between each subcontracted package in your Gantt chart.
2. The previous trade’s work not finished
The dry liner arrives but the insulation isn’t done. The tiler arrives but the screed isn’t dry. Result: they leave and you lose your slot in their diary.
Solution: Check yourself that each package is 100% complete and compliant before calling the next trade.
3. Forgotten service routes
The electrician forgot to run a conduit through a wall? The plumber didn’t allow for the washing machine waste? You find out after the plasterboard is up — and have to cut it all open again.
Solution: Hold a technical walk-round with each trade before 1st fix. Confirm that all service routes (socket positions, water supplies, wastes) are signed off on the drawings.

4. Trades getting in each other’s way
Two trades in the same room at the same time means conflict, errors, and damage.
Rule: One trade per zone at a time. If your house is large enough, the electrician can work downstairs while the dry liner is upstairs. Otherwise, keep to a strict sequence.
The site meeting: your coordination tool
Even in self-build, hold a weekly site meeting — even if it’s just you and one trade over a coffee. The agenda:
- Review progress on each package.
- Identify problems before they become blockers.
- Confirm the programme for the following week.
- List materials to order.
- Write up brief minutes (even five lines by email).
Best practice — Keep a site diary: a photo and three lines every day (what was done, what is causing concern, what is planned tomorrow). It is your best defence in the event of a dispute with a trade, for your self-build insurance, and for keeping the programme on track.
Do you need a project manager?
In partial self-build, you are your own project manager / site manager. You:
- Plan the programme
- Coordinate the trades
- Check the quality of the work
- Sign off each package on completion
If you do not feel confident managing this coordination — especially during second fix when four or five trades follow in quick succession — you can bring in an independent project manager:
| Service | Cost | What they do |
|---|---|---|
| Ad hoc site visits | £100–200 per visit | Quality checks + advice |
| Partial project management | 3–5% of build cost | Trades coordination + oversight |
| Full project management | 8–12% | Everything from design to handover |
Warning — A project manager is not an architect. They do not need an architect’s qualification to coordinate building works. Check their professional indemnity insurance and ask for references from similar projects.
Key takeaways
Sequencing the trades is the critical skill in partial self-build. A single trade placed at the wrong point in the sequence can bring the whole site to a standstill. Master the order (structural to finish, outside to inside), exploit parallel tasks (electrician + plumber 1st fix), and coordinate with a weekly site meeting. Your Gantt chart is your management tool — update it every week.
Checklist: sequencing the trades
- Order of trades confirmed (table above)
- Trades booked for each package (with dates)
- Self-build tasks identified and slotted between professional packages
- Service routes confirmed before 1st fix (socket positions, water supplies, wastes)
- One week of float between each subcontracted package
- Backup contact for every critical trade
- Weekly site meeting scheduled
- Site diary in place (photos + daily notes)
- Quality check before each following package
- Gantt chart updated every week